Customer
FMC Technologies do Brasil LtdaProject
Expansion and adjustment of FMC industrial plant, involving the construction of new units: Warehouse with 4,500 m², Fassub Production Shed with 5,760 m², where eight overhead cranes with capacity between 6 and 50 metric tons were installed, as well as a new substation, and Fassub external area with 10,000 m².Adjustment of the units in operation, building foundations for new equipment at #1 and #2 Headquaters Machine Sheds, installation of roofs and replacement of the tiles at the Headquarters Manufacturing Building, including the installation of two overhead cranes (6- and 12.5- t).